The Pujada Nickel Project: Company Information

Name of Project
PUJADA NICKEL PROJECT
Name of Proponent
Asiaticus Management Corporation (AMCOR)
Project Site
Head Office:
2255 Triplex Bldg. Chino Roces Ave., Makati City, M.M.
Mine Site:
Salinkomot, Sitio Magum, Brgy. Macambol, Mati City Davao Oriental
Legal Basis:
Mineral Production Sharing Agreement (MPSA)
Austral-Asia Link Mining Corporation:
Approved: June 08, 2004

Hallmark Mining Corporation:
Approved: June 08,2004
Memorandum of Agreement (MOA) with the Indigenous People (IP)
MOA between the 7 MPSAs (under AMCOR) and Mandaya Tribal Council and National Commission on Indigenous People (NCIP) R-XI executed on January 07, 2002
Compliance Certificate to FPIC
CCRXI – 04 – 02 – 003 – AMCOR
Issued on February 20, 2004
Environmental Compliance Certificate
Austral- Asia Link Mining Corporation:
ECC-CO- 1303-0008
Approved: Oct.10, 2014

Hallmark Mining Corporation:
ECC-CO- 1409-0019
Approved May 18, 2015
Declaration of Mining Project Feasibility (DMPF)
Approved January 25, 2016
Special Tree Cutting Permit No.
Ref. No. RXI-0001-2016 issued on February 12, 2016
Personnel Strength (t initial production)
Initial employment generated was 746 people
Mineral Resources: (Not PMRC-Compliant)
Class, Ni % WMT % Ni % Co % Fe
>1.7 12,010,460 1.92 0.04 18.54
1.4 – 1.7 30,227,220 1.52 0.04 20.93
1.2 – 1.4 44,000,188 1.29 0.05 23.75
1.0 – 1.2 79,157,340 1.09 0.06 28.56
<1.0 971,541,652 0.47 0.02 12.22
TOTAL 1,136,936,860 0.58 0.03 14.10
Mining Method
“Bench Surface Mining”
Mining Commodity
Nickel laterite ore